The following is the order of the date of the historic development of PT. Kyowa-Indonesia from the first year until now. Sorted by month and year.
- 1995 March, PT. Kyowa Indonesia Established in EJIP Industrial Park as a 100% foreign investment
- 1996 February, Commenced commercial production
- 1997 November, Expanded factory for increase of production
- 1998 Because of Monetary Crisis in 1997, started export DC Product to Japan
- 2003 April, Acquired QS9000
- 2004 April, Bought 2nd Plant in EJIP. In the same year we increased 1 Melting Furnace and Middle Size Machine.
- 2007 On Schedule Lay-out to increase Casting Equipment and preparation to increase Machining equipment in expanded building at Plant 2
- October, Acquired ISO9001: 2000
- 2008 October, 34 Machine for additional Yokairo 1.5 T Machine and increase 10 Casting Machine. Increase 33 Machining Machine to integrate production from Casting ~ Machining. Increase Precision Measurement Machine for Process (3 Dimension, Profile, Circularity)
- 2009 Expanded Building at Plant 1
- 2010 Move Machining equipment and Finishing from Plant 2